Nuclear power costs too much
U.S. nuclear power plants are old and in decline. By 2030, U.S. nuclear power generation might be the source of just 10% of electricity, half of production now, because 38 reactors producing a third of nuclear power are past their 40-year life span, and another 33 reactors producing a third of nuclear power are over 30 years old. Although some will have their licenses extended, 37 reactors that produce half of nuclear power are at risk of closing because of economics, breakdowns, unreliability, long outages, safety, and expensive post-Fukushima retrofits (Cooper 2013. Nuclear power is too expensive, 37 costly reactors predicted to shut down and A third of Nuclear Reactors are going to die of old age in the next 10-20 years.
New reactors are not being built because it takes years to get permits and $8.5–$20 billion in capital must be raised for a new 3400 MW nuclear power plant (O’Grady, E. 2008. Luminant seeks new reactor. London: Reuters.). This is almost impossible since a safer 3400 MW gas plant can be built for $2.5 billion in half the time. What utility wants to spend billions of dollars and wait a decade before a penny of revenue and a watt of electricity is generated?
In the USA there are 104 nuclear plants (largely constructed in the 1970s and 1980s) contributing 19% of our electricity. Even if all operating plants over 40 years receive renewals to operate for 60 years, starting in 2028 it’s unlikely they can be extended another 20 years, so by 2050 nearly all nuclear plants will be out of business.
Joe Romm “The Nukes of Hazard: One Year After Fukushima, Nuclear Power Remains Too Costly To Be A Major Climate Solution” explains in detail why nuclear power is too expensive, such as:
- New nuclear reactors are expensive. Recent cost estimates for individual new plants have exceeded $5 billion (for example, see Scroggs, 2008; Moody’s Investor’s Service, 2008).
- New reactors are intrinsically expensive because they must be able to withstand virtually any risk that we can imagine, including human error and major disasters
- Based on a 2007 Keystone report, we’d need to add an average of 17 plants each year, while building an average of 9 plants a year to replace those that will be retired, for a total of one nuclear plant every two weeks for four decades — plus 10 Yucca Mountains to store the waste
- Before 2007, price estimates of $4000/kw for new U.S. nukes were common, but by October 2007 Moody’s Investors Service report, “New Nuclear Generation in the United States,” concluded, “Moody’s believes the all-in cost of a nuclear generating facility could come in at between $5,000 – $6,000/kw.”
- That same month, Florida Power and Light, “a leader in nuclear power generation,” presented its detailed cost estimate for new nukes to the Florida Public Service Commission. It concluded that two units totaling 2,200 megawatts would cost from $5,500 to $8,100 per kilowatt – $12 billion to $18 billion total!
- In 2008, Progress Energy informed state regulators that the twin 1,100-megawatt plants it intended to build in Florida would cost $14 billion, which “triples estimates the utility offered little more than a year ago.” That would be more than $6,400 a kilowatt. (And that didn’t even count the 200-mile $3 billion transmission system utility needs, which would bring the price up to a staggering $7,700 a kilowatt).
Extract from Is Nuclear Power Our Energy Future, Or in a Death Spiral? March 6th, 2016, By Dave Levitan, Ensia:
In general, the more experience accumulated with a given technology, the less it costs to build. This has been dramatically illustrated with the falling costs of wind and solar power. Nuclear, however has bucked the trend, instead demonstrating a sort of “negative learning curve” over time.
According to the Union of Concerned Scientists, the actual costs of 75 of the first nuclear reactors built in the U.S. ran over initial estimates by more than 200 percent. More recently, costs have continued to balloon. Again according to UCS, the price tag for a new nuclear power plant jumped from between US$2 billion and US$4 billion in 2002 all the way US$9 billion in 2008. Put another way, the price shot from below US$2,000 per kilowatt in the early 2000s up to as high as US$8,000 per kilowatt by 2008.
Steve Clemmer, the director of energy research and analysis at UCS, doesn’t see this trend changing. “I’m not seeing much evidence that we’ll see the types of cost reductions [proponents are] talking about. I’m very skeptical about it — great if it happens, but I’m not seeing it,” he says.
Some projects in the U.S. seem to face delays and overruns at every turn. In September 2015, a South Carolina effort to build two new reactors at an existing plant was delayed for three years. In Georgia, a January 2015 filing by plant owner Southern Co. said that its additional two reactors would jump by US$700 million in cost and take an extra 18 months to build. These problems have a number of root causes, from licensing delays to simple construction errors, and no simple solution to the issue is likely to be found.
In Europe the situation is similar, with a couple of particularly egregious examples casting a pall over the industry. Construction began for a new reactor at the Finnish Olkiluoto 3 plant in 2005 but won’t finish until 2018, nine years late and more than US$5 billion over budget. A reactor in France, where nuclear is the primary source of power, is six years behind schedule and more than twice as expensive as projected.
“The history of 60 years or more of reactor building offers no evidence that costs will come down,” Ramana says. “As nuclear technology has matured costs have increased, and all the present indications are that this trend will continue.”
Nuclear plants require huge grid systems, since they’re far from energy consumers. The Financial Times estimates that would require ten thousand billion dollars be invested world-wide in electric power systems over the next 30 years.
In summary, investors aren’t going to invest in new reactors because:
- of the billions in liability after a meltdown or accident
- there may only be enough uranium left to power existing plants
- the cost per plant ties up capital too long (it can take 10 billion dollars over 10 years to build a nuclear power plant)
- the costs of decommissioning are very high
- properly dealing with waste is expensive
- There is no place to put waste — in 2009 Secretary of Energy Chu shut down Yucca mountain and there is no replacement in sight.
Nor will the USA government pay for the nuclear reactors given that public opinion is against that — 72% said no (in E&E news), they weren’t willing for the government to pay for nuclear power reactors through billions of dollars in new federal loan guarantees for new reactors.
Cembalest, an analyst at J.P. Morgan, wrote “In some ways, nuclears goose was cooked by 1992, when the cost of building a 1 GW plant rose by a factor of 5 (in real terms) from 1972” (Cembalest).
Further topics:
- Nuclear power depends on fossil fuels to exist (Ahmed 2017) ...
- Peak Uranium ...
- Nuclear power is Way too Dangerous ...
- Nuclear power plants take too long to build ...
- A crisis will harden public opinion against building new Nuclear Power Plants ...
- EROEI and decommissioning ...
- Scale ...
- Staffing ...
- Nuclear Proliferation & terrorism targets ...
- Water ...
- NIMBYism ...
- No good way to store the energy ...
- Ramping up and down quickly to balance solar & wind damages nuclear power plants ...
- Breeder reactors. You’d need 24,000 Breeder Reactors, each one a potential nuclear bomb (Mesarovic) ...